Q. 63.9( 19 Votes )

A alone can finis

Answer :

Number of days A required do a piece of work : 10 days


Number of days B required do a piece of work : 15 days


Work done by A in one day:


Work done by B in one day:


Work done by A and B together in a one day: + = =


A and B together take 6 days to complete the work.


A’s share of work is : X 6 =


We know that wages are divided on basis of the share of the work


A’s wage is X 3000 = 1800