Answer :

Given: Number of days required for 175 men to dig a canal 3150m long = 36

To find: Number of men required to dig a canal of 3900m in 24 days.


Formula: = Constant where W = Work, WF = Workforce, T = Time






Gives WF2 = 325


Number of men required to dig a canal of 3900m in 24 days is 325


Rate this question :

How useful is this solution?
We strive to provide quality solutions. Please rate us to serve you better.
Try our Mini CourseMaster Important Topics in 7 DaysLearn from IITians, NITians, Doctors & Academic Experts
Dedicated counsellor for each student
24X7 Doubt Resolution
Daily Report Card
Detailed Performance Evaluation
caricature
view all courses
RELATED QUESTIONS :

<span lang="EN-USAP - Mathematics

<span lang="EN-USAP - Mathematics

<span lang="EN-USAP - Mathematics

<span lang="EN-USAP - Mathematics

<span lang="EN-USAP - Mathematics

<span lang="EN-USAP - Mathematics

<span lang="EN-USAP - Mathematics

<span lang="EN-USAP - Mathematics

<span lang="EN-USAP - Mathematics

<span lang="EN-USAP - Mathematics